SDPW: Midline drainage project to be completed early next year

April 27, 2026 / 3:44 PM
SDPW Midline drainage project to be completed early next year
download-img
Sharjah24 : Sharjah Department of Public Works (SDPW) is implementing the Midline project for the drainage of rainwater and groundwater at a cost of AED 500 million. The project is considered one of the largest strategic developments aimed at enhancing drainage efficiency across many vital areas in the emirate. It is not merely a drainage line, but an integrated engineering system extending over long distances and serving dozens of densely populated areas. Although much of the work is underground, it acts as a protective shield that safeguards the community and ensures the smooth continuity of urban life by preventing water accumulation and maintaining traffic flow.

Integrated engineering system

To ensure high efficiency, the project has been divided into three main interconnected zones. The first zone involves the construction of the main transmission line and secondary lines extending 16 km using micro-tunnelling techniques at depths reaching 20 metres. This forms the backbone of the system, transporting large volumes of water efficiently towards the sea.

Pumping stations and supporting networks

The second zone includes the construction of two main pumping stations—Al Ghubayba and Al Sour—along with supporting networks. Al Ghubayba station has a capacity of 6.2 cubic metres per second and serves multiple areas including Al Ghubayba, Al Tala’a, Al Rifa’a, Al Shahba, Al Darari, Al Tarfa, Dasman, Samnan, parts of Industrial Area 4, Al Wahda Street, Wasit Street, and Abu Shaghara Tunnel. It includes 6.6 km of main collection lines.

Al Sour station has a capacity of 5.7 cubic metres per second, serving areas such as Al Shuwaiheen, Al Ghuwair, Al Musalla, Al Manakh, Al Yarmook, Al Mureijah, Umm Al Tarafa, Al Mahatta, Al Jubail, Al Sour, Al Nad, Al Majaz, Abu Shaghara, and parts of King Faisal Road, with 3.3 km of collection lines.

Marine outfalls and infrastructure

The third zone includes marine outfalls and the construction of 55 inspection chambers with depths ranging between 15 and 20 metres and diameters up to 12 metres, ensuring effective maintenance and safe operation of the network.

Project phases and timeline

The project is being implemented in two phases. The first phase, scheduled for completion by the end of 2026, covers areas such as Al Nad, Abu Danig, Al Mahatta, Al Yarmook, King Abdulaziz Street, and Abu Shaghara Tunnel. The second phase, to be completed in the first half of 2027, will cover additional areas including Al Darari, Al Rifa’a, Al Tarfa, Al Tala’a, Al Shahba, Al Musalla, Al Manakh, Al Ghubayba, Al Ghuwair, Samnan, Dasman, Industrial Area 4, Al Shuwaiheen, Al Jubail, Al Sour, Al Majaz, Abu Shaghara, Al Mureijah, Umm Al Tarafa, and major roads such as King Faisal, Al Wahda, and Wasit.

Advanced technology and sustainability

The project relies heavily on micro-tunnelling, covering 15 km compared to only 800 metres of open excavation to minimise traffic disruption. A total of 5,267 GRP pipes, each 3 metres long with a lifespan exceeding 50 years, have been used. The system operates through gravity flow supported by elevation differences, directing water to pumping stations and then to the sea.

More than 651 workers contributed to the project, achieving two million safe working hours. Covering an area of 4,000 hectares, the project reflects Sharjah’s vision to develop resilient infrastructure capable of handling increased rainfall due to climate change, protecting residential areas and vital roads, and ensuring sustainable, efficient drainage services across the emirate.

April 27, 2026 / 3:44 PM